Explain the need for the dummy activity in the Activity Network

Announcements Posted on
Has your uni kept its promises? Vote now to have your say (you could even win an Apple Watch). 29-05-2015
  1. Offline

    ReputationRep:
    Why is the Dummy Activity leading from activity D necessary ? Could it not be removed and have D join directly to that node as D and B would not be starting from the same place and finishing in the same place ? Or am I missing a rule ?
    Click image for larger version. 

Name:	Thingy AN.png 
Views:	82 
Size:	40.7 KB 
ID:	152188 I Apologise for the need to enlarge
  2. Offline

    ReputationRep:
    (Original post by Mulvibusiness)
    Why is the Dummy Activity leading from activity D necessary ? Could it not be removed and have D join directly to that node as D and B would not be starting from the same place and finishing in the same place ? Or am I missing a rule ?
    Click image for larger version. 

Name:	Thingy AN.png 
Views:	82 
Size:	40.7 KB 
ID:	152188 I Apologise for the need to enlarge
    What do you mean by the Dummy Activity? Are you talking about Activity A?
  3. Offline

    ReputationRep:
    (Original post by magdaplaysbass)
    What do you mean by the Dummy Activity? Are you talking about Activity A?
    No, after activity D there is another dashed line leading from the end of activity D to the beginning of activity E and I'm wondering why that dashed line from the end of activity D to the beginning of activity E has to be there
  4. Offline

    ReputationRep:
    This line is the dummy activity that I need someone to clarify Click image for larger version. 

Name:	Thingy AN.png 
Views:	59 
Size:	40.9 KB 
ID:	152202
  5. Offline

    ReputationRep:
    (Original post by Mulvibusiness)
    No, after activity D there is another dashed line leading from the end of activity D to the beginning of activity E and I'm wondering why that dashed line from the end of activity D to the beginning of activity E has to be there
    The reason for the dashed line is that D is not part of the critical path. The latest finishing time for D is 30 weeks and the duration of D is only 4 weeks, so there is room for activity D to 'float.'
    D cannot be directly joined to B because the table tells you that activity B only follows activity A.
  6. Offline

    ReputationRep:
    Oh Okay thank you for the clarification
  7. Offline

    ReputationRep:
    (Original post by Mulvibusiness)
    Oh Okay thank you for the clarification
    no problem

Reply

Submit reply

Register

Thanks for posting! You just need to create an account in order to submit the post
  1. this can't be left blank
    that username has been taken, please choose another Forgotten your password?
  2. this can't be left blank
    this email is already registered. Forgotten your password?
  3. this can't be left blank

    6 characters or longer with both numbers and letters is safer

  4. this can't be left empty
    your full birthday is required
  1. By joining you agree to our Ts and Cs, privacy policy and site rules

  2. Slide to join now Processing…

Updated: May 29, 2012
New on TSR

Taxing sugar

Should sweet foods subsidise healthy ones?

Study resources
Article updates
x

Think you’ll be in clearing or adjustment?

Hear direct from unis that want to talk to you

Get email alerts for university course places that match your subjects and grades. Just let us know what you’re studying.

Quick reply
Reputation gems: You get these gems as you gain rep from other members for making good contributions and giving helpful advice.