Explain the need for the dummy activity in the Activity Network

Announcements Posted on
Study Help needs new mods! 14-04-2014
Post on TSR and win a prize! Find out more... 10-04-2014
    • Thread Starter
    • 0 followers
    Offline

    ReputationRep:
    Why is the Dummy Activity leading from activity D necessary ? Could it not be removed and have D join directly to that node as D and B would not be starting from the same place and finishing in the same place ? Or am I missing a rule ?
    Click image for larger version. 

Name:	Thingy AN.png 
Views:	73 
Size:	40.7 KB 
ID:	152188 I Apologise for the need to enlarge
    • 2 followers
    Offline

    ReputationRep:
    (Original post by Mulvibusiness)
    Why is the Dummy Activity leading from activity D necessary ? Could it not be removed and have D join directly to that node as D and B would not be starting from the same place and finishing in the same place ? Or am I missing a rule ?
    Click image for larger version. 

Name:	Thingy AN.png 
Views:	73 
Size:	40.7 KB 
ID:	152188 I Apologise for the need to enlarge
    What do you mean by the Dummy Activity? Are you talking about Activity A?
    • Thread Starter
    • 0 followers
    Offline

    ReputationRep:
    (Original post by magdaplaysbass)
    What do you mean by the Dummy Activity? Are you talking about Activity A?
    No, after activity D there is another dashed line leading from the end of activity D to the beginning of activity E and I'm wondering why that dashed line from the end of activity D to the beginning of activity E has to be there
    • Thread Starter
    • 0 followers
    Offline

    ReputationRep:
    This line is the dummy activity that I need someone to clarify Click image for larger version. 

Name:	Thingy AN.png 
Views:	45 
Size:	40.9 KB 
ID:	152202
    • 2 followers
    Offline

    ReputationRep:
    (Original post by Mulvibusiness)
    No, after activity D there is another dashed line leading from the end of activity D to the beginning of activity E and I'm wondering why that dashed line from the end of activity D to the beginning of activity E has to be there
    The reason for the dashed line is that D is not part of the critical path. The latest finishing time for D is 30 weeks and the duration of D is only 4 weeks, so there is room for activity D to 'float.'
    D cannot be directly joined to B because the table tells you that activity B only follows activity A.
    • Thread Starter
    • 0 followers
    Offline

    ReputationRep:
    Oh Okay thank you for the clarification
    • 2 followers
    Offline

    ReputationRep:
    (Original post by Mulvibusiness)
    Oh Okay thank you for the clarification
    no problem

Reply

Submit reply

Register

Thanks for posting! You just need to create an account in order to submit the post
  1. this can't be left blank
    that username has been taken, please choose another Forgotten your password?

    this is what you'll be called on TSR

  2. this can't be left blank
    this email is already registered. Forgotten your password?

    never shared and never spammed

  3. this can't be left blank

    6 characters or longer with both numbers and letters is safer

  4. this can't be left empty
    your full birthday is required
  1. By completing the slider below you agree to The Student Room's terms & conditions and site rules

  2. Slide the button to the right to create your account

    Slide to join now Processing…

    You don't slide that way? No problem.

Updated: May 29, 2012
Article updates
Reputation gems:
You get these gems as you gain rep from other members for making good contributions and giving helpful advice.