    Why is the Dummy Activity leading from activity D necessary ? Could it not be removed and have D join directly to that node as D and B would not be starting from the same place and finishing in the same place ? Or am I missing a rule ?
    Name:  Thingy AN.png
Views: 128
Size:  40.7 KB I Apologise for the need to enlarge
    Offline

    0
    ReputationRep:
    (Original post by Mulvibusiness)
    Why is the Dummy Activity leading from activity D necessary ? Could it not be removed and have D join directly to that node as D and B would not be starting from the same place and finishing in the same place ? Or am I missing a rule ?
    Name:  Thingy AN.png
Views: 128
Size:  40.7 KB I Apologise for the need to enlarge
    What do you mean by the Dummy Activity? Are you talking about Activity A?
    • Thread Starter
    Offline

    0
    ReputationRep:
    (Original post by magdaplaysbass)
    What do you mean by the Dummy Activity? Are you talking about Activity A?
    No, after activity D there is another dashed line leading from the end of activity D to the beginning of activity E and I'm wondering why that dashed line from the end of activity D to the beginning of activity E has to be there
    • Thread Starter
    Offline

    0
    ReputationRep:
    This line is the dummy activity that I need someone to clarify Name:  Thingy AN.png
Views: 94
Size:  40.9 KB
    Offline

    0
    ReputationRep:
    (Original post by Mulvibusiness)
    No, after activity D there is another dashed line leading from the end of activity D to the beginning of activity E and I'm wondering why that dashed line from the end of activity D to the beginning of activity E has to be there
    The reason for the dashed line is that D is not part of the critical path. The latest finishing time for D is 30 weeks and the duration of D is only 4 weeks, so there is room for activity D to 'float.'
    D cannot be directly joined to B because the table tells you that activity B only follows activity A.
    • Thread Starter
    Offline

    0
    ReputationRep:
    Oh Okay thank you for the clarification
    Offline

    0
    ReputationRep:
    (Original post by Mulvibusiness)
    Oh Okay thank you for the clarification
    no problem
 
 
 
Write a reply…

Reply

Submit reply

Register

Thanks for posting! You just need to create an account in order to submit the post
  1. this can't be left blank
    that username has been taken, please choose another Forgotten your password?
  2. this can't be left blank
    this email is already registered. Forgotten your password?
  3. this can't be left blank

    6 characters or longer with both numbers and letters is safer

  4. this can't be left empty
    your full birthday is required
  1. Oops, you need to agree to our Ts&Cs to register
  2. Slide to join now Processing…

Updated: May 29, 2012
TSR Support Team

We have a brilliant team of more than 60 Support Team members looking after discussions on The Student Room, helping to make it a fun, safe and useful place to hang out.

Poll
Who is going to win Bake Off?
Useful resources

Make your revision easier

Maths

Maths Forum posting guidelines

Not sure where to post? Read here first

Equations

How to use LaTex

Writing equations the easy way

Student revising

Study habits of A* students

Top tips from students who have already aced their exams

Study Planner

Create your own Study Planner

Never miss a deadline again

Polling station sign

Thinking about a maths degree?

Chat with other maths applicants

Can you help? Study help unanswered threads

Groups associated with this forum:

View associated groups
Study resources

The Student Room, Get Revising and Marked by Teachers are trading names of The Student Room Group Ltd.

Register Number: 04666380 (England and Wales), VAT No. 806 8067 22 Registered Office: International House, Queens Road, Brighton, BN1 3XE

Reputation gems: You get these gems as you gain rep from other members for making good contributions and giving helpful advice.