Critical Path Analysis problem.

It's been a couple of years since I was taught CPA in Decision Mathematics and I'm trying to tackle a question, where i'm not sure if my diagram is correct so I came here for help!

Activity Duration Predecessor
A 1 -
B 5 -
C 2 -
D 12 B
E 8 B
F 3 B
G 7 A,D
H 12 A,D
I 3 F
J 7 F
K 1 C,J
L 4 H,E,I,K
M 1 C,J



and my answer:

20121220_092616_resized.jpg
Reply 1
And looking at it now.. I see horrible mistakes. Ha
Reply 2
Just realised I sent you the wrong one! mustve got it mixed up. Here is my actual attempt:


CPA.jpg
Reply 3
BUMP