Register  
 
About Us | Help | Sign in
 
   

Revision:Vaiont Dam

From The Student Room

TSR Wiki > Study Help > Subjects and Revision > Revision Notes > Geography > Vaiont Dam


Contents

ORDER OF EVENTS

Prior to the Completion of the Dam

It appears that during the construction of the dam the chief engineer was concerned about the stability of the left bank of the dam, and a number of reports were compiled on this during 1958 and 1959, which identified a possible prehistoric slide on the right bank. Whilst there was considerable discussion of the stability of the valley walls in view of the inclined synclinal form of the strata and the possibility of old slides in this area, it was concluded that deep-seated landslides were extremely unlikely as (see Muller 1964 for a review of this):

  • areas of weakness were not identified in the three test borings;
  • it was assumed that any shear plane would have a 'chairlike' form that would exert a 'braking effect';
  • seismic analyses had suggest that the banks consisted of very firm in-situ rock with a high modulus of elasticity.

Smaller slides in the looser surface layers were considered to be likely, although volumes and velocities of movement were expected to be low.


During the First Filling of the Reservoir

Filling was initiated in February 1960, before final completion of the dam (which occurred in September 1960). By March 1960 the level of the reservoir had reached 130 m above the level of the river, when the first small detachment occurred. Continued filling of the reservoir occurred whilst monitoring of the movements in the banks was undertaken. In October 1960, when the depth of the reservoir had reached 170 metres, a rapid increase in the rate of displacement to approximately 3.5 cm day-1 was observed. At the same time a huge joint of 2 km length opened up, defining an area about 1700 m long and 1000 m wide, suggesting that a very large landslide had been mobilised. On 4 November, with the depth of the reservoir at 180 m, a large failure occurred when 700 000 m 3 of material slid into the lake in about ten minutes. As a result the level of the reservoir was gently dropped back to 135 m. At this point movement reduced to close to 1 mm day-1.


It was realised by the designers of the dam that the large mass of the left bank was inherently unstable. However Muller (1964) states that:


"It appeared hopeless to arrest the slide artificially, because all means that would have had to be applied were beyond human bounds. It was also impossible to either seal the surface of the area, to shift the weight or to cement the rock by means of injections. On the other hand the possibility of accelerating the sliding movement in order to let the entire mass to slide down all at once had to be excluded. The danger arising for the formation upstream of the slide by an uncontrollable level of the storage lake would have been too great."


Thus it was decided that an attempt could be made to gain control of the sliding mass by varying the level of water in the reservoir whilst controlling the joint water thrust within the rock mass by means of drainage tunnels. It was realised that this could lead to the blockage of that section of the reservoir by the landslide mass. However the volume of water in the unblocked (upstream) section would still be sufficient to allow the generation of electricity. Hence a bypass tunnel was constructed on the opposite (right) bank such that if the reservoir was divided into two sections the level of the lake could still be controlled.


It was assumed that by elevating the level of the reservoir in a careful manner movement of the large landslide mass could be initiated. The rate of movement could be controlled by altering the level of the lake. It was realised that a final sudden movement might occur, and it was calculated that, so long as the movement did not exceed a rate that would lead to filling of the reservoir by the landslide in ten minutes or less, over-topping of the dam would be avoided.


First Draw-Down of the Reservoir

Creep had been initiated by the initial filling of the reservoir. As the level was subsequently drawn down, rates of movement decreased from a maximum of about 8 cm day-1 to 3 mm day-1 at a level of 185 m and less than 1 mm day-1 at 135 m. By this time the main landslide mass had moved an average of about 1 m.


Second Filling of the Reservoir

From the beginning of October 1961 through to early February 1962 the water level was raised to 185 m, followed by a phase of slow impoundment such that in November 1962 the level had reached 235 m. During the early part of this phase velocities did not substantially increase, but by the end of the phase velocities had increased to 1.2 cm day-1.


Second Draw-Down of the Reservoir

In November 1962 a second lowering of the level was slowly undertaken, with the water depth decreasing to 185 m after four months. Initially displacements remained high but in December they began to reduce and, by early April when the water height had reached 185 m, the rate was effectively zero. The experiences gained from the second phase of filling and the subsequent draw-down confirmed to the engineers that control of the landslide was possible by altering the level of the reservoir. In consequence a third filling of the reservoir was undertaken.


Third Filling of the Reservoir

Between April and May 1963 the reservoir level was rapidly increased to 231 m. Slight increases in velocity were noted, but rates never exceeded 0.3 cm day-1. During June the level was increased to 237 m and the rate of displacement increased to 0.4 cm day -1. In mid July the level reached 240 m and some of the control points indicated small increases in displacement to 0.5 cm day-1. The level was maintained through to mid-August, but during this time velocities increased to 0.8 cm day-1. In the latter part of August the level was increased once more such that by early September the depth of water was 245 m. In some parts of the slide velocities increased to as much as 3.5 cm day-1.


Third Drawing Down of the Reservoir

In late September the water level was slowly dropped to bring the rates of creep back under control. By October 9 a depth of 235 m was reached. However velocities of movement continued to slowly increase, and by October 9 rates of up to 20 cm day-1 were recorded.


Catastrophic Failure

At 22:38 GMT on October 9 1963 catastrophic failure of the landslide occurred. The entire mass slid approximately 500 m northwards at up to 30 m sec-1. The mass completely blocked the gorge to a depth of up to 400m , and it travelled up to 140 m up the opposite bank. Movement of the landslide mass ceased after a maximum of 45 sec. At the time the reservoir contained 115 million m3 of water. A wave of water was pushed up the opposite bank and destroyed the village of Casso, 260 m above lake level before over-topping the dam by up to 245 m. The water, estimated to have had a volume of about 30 million m3, then fell more than 500 m onto the villages of Longarone, Pirago, Villanova, Rivalta and Fae, totally decimating them. A total 2500 lives were lost. However the dam was not destroyed and is still standing today. The by-pass tunnel is used for the generation of HEP.


CAUSES OF FAILURE

Since the catastrophic failure, a huge range of work has been undertaken on the causes of the failure. Initially the was a large amount of speculation about the location of the sliding surface, but more recent studies have confirmed that it was located in thin (5 - 15 cm) clay layers in the limestone. It is claimed by some that as such it represents a reactivation of an old landslide (Hendron and Patten, 1985; Pasuto and Soldati, 1991), whilst others claim that it was a first-time movement (Skempton, 1966; Petley, 1996). It is likely that increasing the level of the reservoir drove up pore pressures in the clay layers, reducing the effective normal strength and hence the shear resistance. Resistance to movement was created by the chair-like form of the shear surface. Dropping the level of the reservoir induced hydraulic pressures that increased the stresses as water in the jointed limestone tried to drain. It has been estimated that the total thrust from this effect was 2 - 4 million tonnes (!?) (Muller, 1964). Failure occurred in a brittle manner, inducing catastrophic loss of strength. The speed of movement is probably the result of frictional heating of the pore water in the clay layers


Comments

These notes are aimed at students studying for Edexcel (B) Unit 5 - Hazards, though will be suitable also for people studying with different exam boards and at different levels.


They were originally submitted by wackojacko in this thread on TSR Forums.

collapse
Recent Threads
 
collapse Will I get into Warwick / St Andrews / Bristol?
started by: joshmohoboob
forum: Economics
replies: 1
last post: 1 Minute Ago
collapse Strangest/cheekiest things you've said to a teacher
started by: Kezzi
replies: 98
last post: 1 Minute Ago
collapse Girls and the word 'sweet'??
started by: Anonymous
replies: 11
last post: 1 Minute Ago
collapse ca fait....
started by: hazzypants
replies: 5
last post: 2 Minutes Ago
collapse January Exams
started by: Da_hopeful_1
replies: 11
last post: 3 Minutes Ago
 
Article Updates