Original post by NotNotBatman
Because once it reaches T, the route has ended, so there's no need to add 2 on to the last arcs of the route. Also, you add 2 to every arc except GT and HT, not only the ones on the shortest route, as you'd have to do it prior to doing dijkstra's algorithm, that's why it's not added to GT and HT and not just one or the other.


Ah I see, thanks so much :smile:
How do you find the shortest route in Dijkstra's algorithm without going through a particular arc that would be included in the shortest route ? Like in question 6(c):
https://d0247e65b1a6ead8e6286cd43803e643462f2b31.googledrive.com/host/0B1ZiqBksUHNYNlBRQkZFLXdQS0E/June%202011%20QP%20-%20D1%20Edexcel.pdf
Original post by NotNotBatman
How do you find the shortest route in Dijkstra's algorithm without going through a particular arc that would be included in the shortest route ? Like in question 6(c):
https://d0247e65b1a6ead8e6286cd43803e643462f2b31.googledrive.com/host/0B1ZiqBksUHNYNlBRQkZFLXdQS0E/June%202011%20QP%20-%20D1%20Edexcel.pdf


I don't think there's any particular method unfortunately, I think you just have to keep trial and erroring to see which route is the shortest :/
Original post by economicss
I don't think there's any particular method unfortunately, I think you just have to keep trial and erroring to see which route is the shortest :/


Well that's a shame. Thanks for the help.
When you draw an precedencd table and the graph, how do you deduce the critical activities?
Original post by Pablo Picasso
When you draw an precedencd table and the graph, how do you deduce the critical activities?


The float of the activity, calculated by the (late event time at the head - activity duration - early event time at tail), should be equal to 0.
Please could anyone explain question 6d here https://d0247e65b1a6ead8e6286cd43803e643462f2b31.googledrive.com/host/0B1ZiqBksUHNYNlBRQkZFLXdQS0E/January%202015%20(IAL)%20QP%20-%20D1%20Edexcel.pdf how do you know what objective line equation to use since the objective line I drew didn't lead to the correct answer, thanks :smile:
Also does anyone know please whether questions like 8d and 8e https://d0247e65b1a6ead8e6286cd43803e643462f2b31.googledrive.com/host/0B1ZiqBksUHNYNlBRQkZFLXdQS0E/January%202004%20QP%20-%20D1%20Edexcel.pdf are in the spec, not seen questions like them before, thanks :smile:
Original post by economicss
Also does anyone know please whether questions like 8d and 8e https://d0247e65b1a6ead8e6286cd43803e643462f2b31.googledrive.com/host/0B1ZiqBksUHNYNlBRQkZFLXdQS0E/January%202004%20QP%20-%20D1%20Edexcel.pdf are in the spec, not seen questions like them before, thanks :smile:
The spec changed back in 2009 so any past papers before that may have some stuff not in the spec.However question 8d and 8e look okay to do
(edited 7 years ago)
Is the any difference between the IAL spec and the UK spec?


Posted from TSR Mobile
Original post by Glavien
Is the any difference between the IAL spec and the UK spec?


Posted from TSR Mobile


No.
How would you do part (d) question 5 of the January 2006 paper? I would've just guessed through trial and error but there must be a better way right?

Paper: https://d0247e65b1a6ead8e6286cd43803e643462f2b31.googledrive.com/host/0B1ZiqBksUHNYNlBRQkZFLXdQS0E/January%202006%20QP%20-%20D1%20Edexcel.pdf
(edited 7 years ago)
Original post by GarlicBread01
The spec changed back in 2009 so any past papers before that may have some stuff not in the spec.However question 8d and 8e look okay to do


Thank you, I understand 8d now but how would you find the total time needed to complete the project please, as we don't have any early or late event times? Thanks :smile:
Original post by economicss
Please could anyone explain question 6d here https://d0247e65b1a6ead8e6286cd43803e643462f2b31.googledrive.com/host/0B1ZiqBksUHNYNlBRQkZFLXdQS0E/January%202015%20(IAL)%20QP%20-%20D1%20Edexcel.pdf how do you know what objective line equation to use since the objective line I drew didn't lead to the correct answer, thanks :smile:


Please could anyone help with this one? :smile: Really struggling with it, thanks!
What the?!

Can someone please confirm that Ex 5A question 4 (Chapter 5 - Critical Path Analysis) shows the same activity network in their D1 edexcel textbook as is on the solutionbank here?
https://86495a24d9b181f09087f4168bceb629c30e8d9b.googledrive.com/host/0B1ZiqBksUHNYYzJJZms0aVJZTW8/CH5.pdf
My textbook has a completely different arrangement of letters I,K,J and L.

Thanks!
Original post by tripleseven
What the?!

Can someone please confirm that Ex 5A question 4 (Chapter 5 - Critical Path Analysis) shows the same activity network in their D1 edexcel textbook as is on the solutionbank here?
https://86495a24d9b181f09087f4168bceb629c30e8d9b.googledrive.com/host/0B1ZiqBksUHNYYzJJZms0aVJZTW8/CH5.pdf
My textbook has a completely different arrangement of letters I,K,J and L.

Thanks!


Yeah, it's different in the textbook and the answers at the back is wrong, J depends on G, not H.


They didn't, it's just written under CE, to show that it has the same weight, so it doesn't matter what order it's written in, 'NOT CE' is just referring to the arc CE, but BE is added.
Original post by NotNotBatman
They didn't, it's just written under CE, to show that it has the same weight, so it doesn't matter what order it's written in, 'NOT CE' is just referring to the arc CE, but BE is added.


Ohhh, thanks for that. :smile:
Original post by Glavien
How would you do part (d) question 5 of the January 2006 paper? I would've just guessed through trial and error but there must be a better way right?

Paper: https://d0247e65b1a6ead8e6286cd43803e643462f2b31.googledrive.com/host/0B1ZiqBksUHNYNlBRQkZFLXdQS0E/January%202006%20QP%20-%20D1%20Edexcel.pdf


The tagging system isn't working properly for me.

For this question you would just have to look at the area of the Gantt chart with the most overlaps. If I were doing this question, I would look around the place where there's a lot of activities occurring with minimal floats, as there's not a lot of room for manoeuvre and then consider an interval of time, where activities must be taking place.