For a scheduling diagram can you start an activity before the early event time? For example if the early and late start time if 4 and the early and late finish time is 7 and 10 and the activity time is 2 could I start this activity at day 3? Hope that makes sense?
For a scheduling diagram can you start an activity before the early event time? For example if the early and late start time if 4 and the early and late finish time is 7 and 10 and the activity time is 2 could I start this activity at day 3? Hope that makes sense?
No I don't think you can because the early event time allows for the completion of preceding activities. So if activity B depends on the completion of activity A then if activity B were to start early it would not give enough time for A to be completed. Therefore it wouldn't work- hopefully it makes sense
No I don't think you can because the early event time allows for the completion of preceding activities. So if activity B depends on the completion of activity A then if activity B were to start early it would not give enough time for A to be completed. Therefore it wouldn't work- hopefully it makes sense