#1
heys guys... need some help.
on the cascade charts, should u have to show the type of float an activity has? if so how do you do it?
0
AT82
Badges: 0
Rep:
? You'll earn badges for being active around the site. Rep gems come when your posts are rated by other community members.
#2
Report 18 years ago
#2
(Original post by littleone)
heys guys... need some help.
on the cascade charts, should u have to show the type of float an activity has? if so how do you do it?
Is this Project Management? I've never come across a cascade chat before, only pert and gannt charts.
0
littleone
Badges: 0
Rep:
? You'll earn badges for being active around the site. Rep gems come when your posts are rated by other community members.
#3
Report Thread starter 18 years ago
#3
umm its the same thing as gannt. the ocr board calls them cascade
0
AT82
Badges: 0
Rep:
? You'll earn badges for being active around the site. Rep gems come when your posts are rated by other community members.
#4
Report 18 years ago
#4
(Original post by littleone)
umm its the same thing as gannt. the ocr board calls them cascade
I've done a lot of gannt chat stuffs but I think I've always used a pert chart to show the float. I'll see if I can find some old notes (I got 23/24 for projece mangement at college) so I would like to think it was one of better subjects, I only got 60% when I did it at uni though.
0
_EMMA_
Badges: 16
Rep:
? You'll earn badges for being active around the site. Rep gems come when your posts are rated by other community members.
#5
Report 18 years ago
#5
well the definition, taken from my school book:
Critical path The sequence of activities which determines the minimum time needed to complete a project.

with other words when you have done an analysis of a network, written down the time different things takes to do, you can count out the critical path, this is the path where you can't be delayed in the work.
0
Perplexed
Badges: 8
Rep:
? You'll earn badges for being active around the site. Rep gems come when your posts are rated by other community members.
#6
Report 18 years ago
#6
(Original post by littleone)
heys guys... need some help.
on the cascade charts, should u have to show the type of float an activity has? if so how do you do it?
If the activity has a float, you draw it as a bar (the same as for those activities without a float), then draw a dotted line in front of it, at the point where the float ends.

Whether that'll help you, I'm unsure. I'm not entirely clear what you're getting at.
0
X
new posts
Back
to top
Latest

How are you feeling about your results?

They're better than I expected (175)
40.89%
They're exactly what I expected (112)
26.17%
They're lower than I expected (141)
32.94%

Watched Threads

View All