    Please can you help me with the following scenario...

    Early on Friday morning, ABC Ltd was advised by NottEast Railways that the oak veneered panels had arrived at Nottingham railway station. ABC Ltd duly authorised NottEast Railways to deliver the panels to Bendit Ltd which went to the station to collect them. However, when Bendit Ltd arrived it was discovered that thieves had broken into one of the containers and stolen 100 of the panels. This theft occurred shortly before ABC Ltd authorised NottEast Railways to deliver the goods to Bendit Ltd. The price of oak veneered panels is continuing to rise and Carlton Ltd is insisting upon taking delivery of the remaining 150 panels at the contract price. Bendit Ltd has itself agreed to accept delivery of the remaining 150 panels from ABC Ltd but now intends to sell these to another customer at a much higher price.

    When did property pass? After the delivery of goods but before authorisation to release them OR after the delivery of goods and after authorisation . Would the carrier bear any risk under section 32 (1) of SGA 1979?

    Please explain, thanks.
    • Very Important Poster
    Offline

    19
    Very Important Poster
    Make a timeline.

    Read the section and follow title.
    Offline

    0
    ReputationRep:
    i think dont think property can pass if you reserve the right of disposal so because the thieves stole the panels before authorisation it didnt pass? and also because they were delivered to nottingham railway that can be regarded as a specified place so s.32(1) doesnt apply so risk remains with seller? im not 100% sure tbh
    Offline

    0
    ReputationRep:
    (Original post by lawstudent102)
    Please can you help me with the following scenario...

    Early on Friday morning, ABC Ltd was advised by NottEast Railways that the oak veneered panels had arrived at Nottingham railway station. ABC Ltd duly authorised NottEast Railways to deliver the panels to Bendit Ltd which went to the station to collect them. However, when Bendit Ltd arrived it was discovered that thieves had broken into one of the containers and stolen 100 of the panels. This theft occurred shortly before ABC Ltd authorised NottEast Railways to deliver the goods to Bendit Ltd. The price of oak veneered panels is continuing to rise and Carlton Ltd is insisting upon taking delivery of the remaining 150 panels at the contract price. Bendit Ltd has itself agreed to accept delivery of the remaining 150 panels from ABC Ltd but now intends to sell these to another customer at a much higher price.

    When did property pass? After the delivery of goods but before authorisation to release them OR after the delivery of goods and after authorisation . Would the carrier bear any risk under section 32 (1) of SGA 1979?

    Please explain, thanks.


    So your a NTU student then
 
 
 
  • See more of what you like on The Student Room

    You can personalise what you see on TSR. Tell us a little about yourself to get started.

  • Poll
    Brussels sprouts
  • See more of what you like on The Student Room

    You can personalise what you see on TSR. Tell us a little about yourself to get started.

  • The Student Room, Get Revising and Marked by Teachers are trading names of The Student Room Group Ltd.

    Register Number: 04666380 (England and Wales), VAT No. 806 8067 22 Registered Office: International House, Queens Road, Brighton, BN1 3XE

    Quick reply
    Reputation gems: You get these gems as you gain rep from other members for making good contributions and giving helpful advice.