    Assume that there is a delay of 5 weeks in completing activity F. Analyse one action that the Project Manager could take to avoid exceeding the current length of the critical path.
    • Very Important Poster
    Online

    21
    ReputationRep:
    Very Important Poster
    (Original post by zaky_k14)
    Assume that there is a delay of 5 weeks in completing activity F. Analyse one action that the Project Manager could take to avoid exceeding the current length of the critical path.
    Not that this is my area of expertise, but without the full question and what these activities are no one will be able to help,
 
 
 
Reply
Submit reply
Turn on thread page Beta
Updated: February 2, 2017
Poll
“Yanny” or “Laurel”

The Student Room, Get Revising and Marked by Teachers are trading names of The Student Room Group Ltd.

Register Number: 04666380 (England and Wales), VAT No. 806 8067 22 Registered Office: International House, Queens Road, Brighton, BN1 3XE

Write a reply...
Reply
Hide
Reputation gems: You get these gems as you gain rep from other members for making good contributions and giving helpful advice.