Can somebody help im stuck constructing my CPA
im doing a project
im putting togeather the project report
task 3.1 is assemble project report and write section it cannot be completed until the other task (1.1-2.3) have been completed. but 3.1 depend on 1.1 and not on the other tasks, because the tasks can be done and put in the report any time. im stuck on constructing my CPA and where the arrows go of the other tasks go. 3.1 has really got me stuck.
Task Activity Predecessor Duration (weeks)
1.1 N/A 1
1.2 1.1 2
1.3 1.2 1
1.4 1.1 13
2.1 1.1 2
2.2 1.2 & 2.1 2
2.3 2.2 1
2.4 1.1 13
3.1 1.1 6
3.2 3.1 2
im doing a project
im putting togeather the project report
task 3.1 is assemble project report and write section it cannot be completed until the other task (1.1-2.3) have been completed. but 3.1 depend on 1.1 and not on the other tasks, because the tasks can be done and put in the report any time. im stuck on constructing my CPA and where the arrows go of the other tasks go. 3.1 has really got me stuck.
Task Activity Predecessor Duration (weeks)
1.1 N/A 1
1.2 1.1 2
1.3 1.2 1
1.4 1.1 13
2.1 1.1 2
2.2 1.2 & 2.1 2
2.3 2.2 1
2.4 1.1 13
3.1 1.1 6
3.2 3.1 2
Last edited by mlm1234; 7 months ago