Could someone please explain in detail how to answer the last part of the question below?:

http://www.ocr.org.uk/download/pp_11_jun/ocr_66520_pp_11_jun_gce_4771.pdf

It's on page 4.
Thanks :smile:
Original post by chroli1
Hi,

Could someone please explain in detail how to answer the last part of the question below?:

http://www.ocr.org.uk/download/pp_11_jun/ocr_66520_pp_11_jun_gce_4771.pdf

It's on page 4.
Thanks :smile:


If the construction budget is increased, this will give you a different constraint relating to the budget, and then repeat the process for finding the maximum number of ....
Reply 2
Thanks :smile:
Reply 3
Original post by chroli1
Hi,

Could someone please explain in detail how to answer the last part of the question below?:

http://www.ocr.org.uk/download/pp_11_jun/ocr_66520_pp_11_jun_gce_4771.pdf

It's on page 4.
Thanks :smile:


Let x1 be the number of large houses and x2 for the standard houses
Constraints:
Nonnegitivty
x1>0
x2>0
The market
2x1<=x2 -> 2x1-x2<=0
The area
200x1+120x2<=12000
The budget
60000x1+50000x2<=42500000
Draw these line in the (x1,x2) coordinate system