It takes 15 days, to complete a task, for 4 people working 8 hours a day. How many days would it take 5 people working 6 hours a day? Assume the working rates are all the same.
Please post your attempt. The intent is to help people answer a question, not give-out the answers.

Hint: How many people-hours does the task take?
Original post by 12diaconud
It takes 15 days, to complete a task, for 4 people working 8 hours a day. How many days would it take 5 people working 6 hours a day? Assume the working rates are all the same.


Work out the number of hours overall, ie no. of people * no.of hours * no. of days, then divide through by the new numbers of people ans hours per day